Cheung Shun Street Jobsite Birdview
PROJECT SUMMARY

Scope of Works:

  • Site formation and ELS works including excavation and shoring installation
  • Marine dumping works
  • Pile cap construction works

Contract Sum:

  • $90.5M

Contract Period:

  • April 2019 – November 2019

Total 7 layers of shoring / strutting system with approximate excavation volume of nearly 68,000m3 which consists of 35,000m3 marine mud are carried out with telescoping excavator for 18m deep excavation.

SNAPSHOT
19091801_Cheung Shun Street
19091802_Cheung Shun Street